Fairway Cromer

Current status: Construction continues to progress, with programme planning currently being updated ahead of the next construction meeting.
Timeline: Practical Completion is currently scheduled for March 2027.
Key updates: Planning is underway for upcoming milestone activities, including crane erection anticipated around mid-February, with promotional and construction update content to be produced at key stages of the build.
Next steps: Finalise the updated construction programme, confirm crane erection timing, and align on messaging and content strategy for ongoing construction updates and milestone communications.

Related Posts

Due for completion September 2026

Current status: Construction is progressing well, with ramp entry and all ground floor slab works now complete. Ground floor concrete…

Due for completion 2026

Current status: Works are progressing well, with internal building works now approximately 95% complete and public domain works and landscaping…

Due for completion 2027

Current status: Construction is progressing as scheduled, with façade external finishes now completed and works transitioning to scaffold dismantling.Timeline: There…

Current status: Construction at Casa Delmar (Dee Why) is progressing steadily and continues at pace, with the apartment buildings now…

Get Your Free
Digital Appraisal

Receive an instant estimate of your home value based on current Northern Beaches market conditions. It is fast, easy and completely obligation free.