Current status: Construction is progressing well, with ramp entry and all ground floor slab works now complete. Ground floor concrete walls are currently underway and sitting at approximately 35% complete.
Timeline: There are no changes to the current programme at this stage. Contract Practical Completion remains 23 June 2026, with approved EOTs of 54 days bringing the revised Practical Completion date to 7 September 2026.
Key updates: Recent works completed include ramp entry, ground floor formwork, reinforced steel, electrical conduits, plumbing penetrations, and the ground floor concrete pour (all 100% complete). No design issues or critical issues have been reported, and there have been no accidents or incidents on site.
Next steps: Continue progressing ground floor concrete walls and associated structural works, with ongoing monitoring of safety and site inductions for all contractors and visitors